Plumbing & Fire Protection - Post 3 of 3
Flexible Retail Center Design - Plumbing & Fire Protection –

The design for plumbing in a retail shell building is typically straight forward; however there are several considerations which should be reviewed when designing the water, sanitary, fire protection and gas (where applicable) systems for the overall center.

Water - When considering domestic water service, it is important to bear in mind the type of tenants that will be served. Depending on the local pressure and water flow, a typical restaurant space could require a 2” line as opposed to a retail space which might only require a ¾” line as long as tank type toilets are utilized. The most flexible design involves working with the developer to consider a worst case scenario as far as water usage is concerned. This worst case can be utilized to size the overhead pipe size that can be run with a series of 1” and 2” taps/valves to allow for ease of future tenant connections. Typically as a cost saving measure, deduct meters are installed under the tenant installation, as all of the valves may not be utilized.

Sanitary - Sanitary waste systems for most retail facilities are very basic with a 4-inch building sanitary main being typically sufficient. There are three basic options for sanitary design. The first is to run under-slab the entire length of the facility with the sanitary main providing cleanouts only at code required locations. This pipe can be run in either a 10ft “leave-out” (no concrete slab) in the rear of the space or it can have the slab poured completely over it. While this approach has an initial low cost, it is often more than offset by slab cut/patch and longer tenant construction timeframes.

A second approach to sanitary, if the landlord has a good idea of the types of tenants they will be attracting, is to run the entire length with the main sanitary and providing restroom stubs in a few key locations for possible tenants who need to get in their space quickly.

Once again, food service facilities will have additional requirements - specifically, the need for a grease interceptor and related grease-laden waste piping. Unless a specific tenant is known, grease interceptors are not typically designed under the shell package. While there are many ways to handle the grease waste, the most flexible approach if a space has the potential to be a restaurant is to provide two stubs out of the facility in case the grease interceptor must be located outside of the space.
Fire Protection - Typically under the shell design a main riser will be installed and in some cases a line will be installed along the entire rear of the facility. The logical question is how big should the line be (both the incoming and the overhead). More than any other aspect of the design, this is dependent upon the available flow and pressure from the local utility. Once the information is acquired from the utility, the sizing of both the main entry and the main riser size can be calculated based on the size of the spaces and there intended use, or worst case usage if tenants are unknown.
Gas – When gas is available at a site there are two primary design decisions that must be made with regards to gas service for a retail shell building. The first is the overall requirements of the facility and the second is distribution of gas piping. As noted with water service above, based on the worst case anticipated needs of the developer, the main gas service can be sized. Ensuring that enough gas is brought to the site is critical as acquiring additional gas after pavement is down can be extremely expensive. The distribution of gas piping is dependent upon the selections made during the HVAC design phase. If gas is needed in the shell space, there are two options for gas piping. The gas pipe and associated metering can either be all sized for retail tenants, all for restaurant tenants, or a combination based on the developers expectations for each space.

As you can see, one set of design parameters will not fit the plumbing requirements of all retail centers; however, a little planning ahead can increase the facility flexibility for both the developer and the future tenants.

Flexibility? So flexibility is dependent upon your perspective. One extreme is no utilities provided, which is a low upfront cost approach at the sacrifice of tenant build-out timing and possible damage to the integrity of your building. While the other extreme provides utilities as if spaces were almost ready to occupy – this approach costs more upfront and limits flexibility but it does speed up tenant occupancy. The conclusion being there is no “one size fits every retail center” solution; however, a careful analysis of each of these components will lead to the most flexibility for your next center.

Trent Beighle, PE is the president of PE-Services. For further information contact Trent at trent@pe-services.com or Roger Butler, PE at roger@pe-services.com.




Client Login Careers Subscribe to Our Newsletter twitter and facebook
COPYRIGHT ©2010 PE-SERVICES.
ALL RIGHTS RESERVED.